Cimego Basin: 26,000 mc of Sediment Removed

Cimego Basin: 26,000 mc of Sediment Removed

In November 2024, the sediment removal works from the Cimego basin, located in the Municipality of Borgo Chiese and supplying the Storo hydroelectric power plant managed by Hydro Dolomiti Energia, were completed. Between June 2023 and November 2024, approximately...
Dredging of the Vizze Dam

Dredging of the Vizze Dam

Dredging work is currently underway at the Vizze Dam, involving the removal of approximately 3,000 m³ of sediment, with the material being returned to the nearby disposal basin constructed with sheet piles....
Burgoni at Isola Serafini

Burgoni at Isola Serafini

The installation of 170 burgons is currently underway at Italy’s largest run-of-river hydroelectric plant: the Isola Serafini weir. Using a special pontoon with a bottom-opening mechanism, the burgons are placed, which are made with a geotextile covering, a...